I said I'd start it on the first day of Spring and I planned on having it done by the end of April. Today is April 13th (remember to file taxes!) and we are nearly done with it. Today I might pick up the carpet, which is a means to reach the end.

Nursery

We have done the following:
  • Cleaned out the room.
  • Ripped down old drywall.
  • Replaced the window.
  • Spray paint the radiator a solid color.
  • Rehung drywall.
  • Mud and sand the drywall.
  • Finish the window in drywall.
  • Paint the ceiling and walls in two colors of paint.
  • Paint the closet white.
  • Replace two outlets.
  • Add a light switch.
  • Install a ceiling fan (twice).
  • Add the ceiling trim.
  • Install window trim.
  • Install window sill.
  • Paint closet and room doors.
  • Saw off the bottoms of the doors in anticipation of new carpet.
 So we have the following left to do:
  • Install carpet padding.
  • Install new carpet.
  • Reinstall painted baseboard.
  • Install closet and room door trip.
  • Reinstall closet and room doors.
  • Finish ceiling trip.
  • Install corner trim.
  • Bring in baby furniture such as a crib, dresser, etc. (what Rachel calls "The fun part")
So I think I'll make my April 30th deadline way before. And August 4th is the day, the day in which our daughter is due. :)